Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Item

Responsible Party

Time estimate

Completion Date

Location inspection

CIS-Jessica

2 hr

4-27-11

Switchport inventory

CIS-Scott

 

 

Create new VLan

CIS-Scott

1 hr

 

Program switchports

CIS-Scott

2 hr

 

Assign machines IP addresses

CIS-Scott

1 hr

 

1 wire pulled - Auto Lab

CADI-Dennis K

  

07-18-11

1 wire pulled - Dairy Barn

CADI-Dennis K

  

07-14-11

2 wires pulled - Bush 307

CADI-Dennis K

  

07-12-11

Smith Hall wire repair or pull 2

CADI-Dennis K

  

07-14-11

Termination in data closet

CIS

3 hr  

07-18-11

Certification

CIS

4 hr  

07-18-11

Patch cable (wall to machine)

Vendor?

 

 

Patch cable (panel to switch)

CIS

3 hr

 

Server/Software

CIS? CBORD?

 

the PO to CBORD for the vending software was sent on 4/28/11.
This will be put in place after 7/1/11 due to the new budget year for
CADI which begins on 7/1/11.  Also included in the PO for the vending is
the two card readers needed for the "Printing" project.

Test swipe

CADI?

 

We can not do anything with online vending until our contract ends with Next Gen on
8/1/11.  We will proceed as soon as possible after that with Coke to get this project
up and running and in place by the time school opens at the end of the month.  I will need IP addresses to provide to CBORD for Odyssey PCS.

...